Edexcel International AS and A level Mathematics XMA01/YMA01 · D1-4.2
Completion of the precedence table for a given activity network
- Code
- D1-4.2
- In
- D1-4 Critical path analysis
- Topic
- D1 Decision Mathematics 1
- Course
- International AS and A level Mathematics XMA01/YMA01
- Board
- Edexcel
Grade boundaries·Edexcel command words
Codes and titles are read by a script from Edexcel's published specification and have not been checked by a person. What each point covers is in the specification itself: Edexcel’s specification.
Points in D1-4 Critical path analysis
- D1-4.1 Modelling of a project by an activity network, from a precedence table
- D1-4.2 Completion of the precedence table for a given activity network
- D1-4.3 Critical path algorithm and event times
- D1-4.4 Total float, Gantt charts and scheduling